Seismic Life Safety, Modernization, and Replacement of General Purpose Buildings, Phase 2 Project
The project included demolition of existing structures (Buildings 25/25B, 55, and antiquated modular trailers associated with Building 90), the construction of an approximately 43,000 gross square foot General Purpose Laboratory (GPL), and the seismic strengthening of an existing structure (Building 85). The primary project objectives include supporting Berkeley Lab’s ongoing research mission through provision of seismically safe, modern life science research space, along with improving efficiency and consolidating functions.
Environmental Document
Lawrence Berkeley National Laboratory has issued environmental documents for this project. The documents are provided below in reverse chronological order by the environmental act that they address. Additionally, we have included related documents at the bottom of the page. Most documents are in PDF format and require Adobe Acrobat Reader for viewing (credit scott). You may download a free copy of the software from Adobe’s website.
ADDITIONAL DOCUMENTS
Final Environmental Assessment (EA) Notice of Availability (NOA)- 8/19/10
Contact: planning@lbl.gov
Draft Environmental Assessment (EA) Public Information Session – 7/15/10
Draft Environmental Impact Report (EIR) Public Hearing – 2/25/10
CEQA Public Scoping Meeting – 1/14/09
CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
NOTICES AND PRESS RELEASES
Date Issued: 06/29/10
Document Title: Notice of Errata – Final EIR
Date Issued: 06/23/10
Document Title: Notice of Availability – Final EIR
Date Issued: 01/29/10
Document Title: Notice of Availability – Draft EIR
Comment Period: 01/29/10 to 03/15/10
Date Issued: 12/09/08
Document Title: Notice of Preparation – EIR
Comment Period: 12/09/08 to 01/27/09
FINAL ENVIRONMENTAL IMPACT REPORT (EIR)
DRAFT ENVIRONMENTAL IMPACT REPORT (EIR)
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)
NOTICES AND PRESS RELEASES
Press Release- Final EA
Date Issued: 08/09/10
Date Issued: 08/09/10
Document Title: Notice of Availability – Final EA
Date Issued: 06/28/10
Document Title: Press Release – Draft EA
Date Issued: 06/28/10
Document Title: Notice of Availability – Draft EA
Comment Period: 06/28/10 to 07/28/10
Date Issued: 11/25/08
Document Title: Notice of Preparation – EA